A. The following work process in SAP R/3

  • Dialog (D): each dispatcher needs at least 2 dialog work processes (not shown
    above)
  • Spool (S): at least 1 per R/3 System (more than 1 per dispatcher allowed)
  • Update (V): at least 1 per R/3 System (more than 1 per dispatcher allowed)
  • Background (B): at least 2 per R/3 System (more than 1 per dispatcher allowed)
  • Enqueue (E): exactly 1 per R/3 System (only 1 E work process is required and
    allowed)